We ask that you please close your windows during the pressure washing phase. We also request you remove all items from your deck and away from the exterior walls. All items that can’t be removed from the deck can be placed in the centre of the deck and covered to allow access to the exterior walls.
The following is the schedule of pressure washing:
May 26 - Units 1-7 and it will take 4 days
May 30 - Units 8-15 and it will take 4 days
We will be working sequentially. Further updates will be made when we move to the next units.
Thanks in advance,
Greg